Compute deals: who buys capacity from whom

Contracts for AI compute between labs, neoclouds, hyperscalers, chip vendors and the lenders behind them. Each row states what the source states: contract value, capacity, term. Headline figures often include options and later phases; where the source says "up to", so does the note.

Data checked 10 Nov 2026How deal figures are recorded

Deals on record170144 confirmed, 26 reported
Confirmed contract value$1.6Tcapacity and supply deals with a stated value
Capacity stated74.21 GWin deals that disclose MW
Debt financings38$218B confirmed

Where the contracted dollars go

BuyerProviderAnthropic → Amazon Web Services: $119BAnthropic → Microsoft: $35BAnthropic → Broadcom: $182BAnthropic → SpaceXAI: $121BAnthropic → Google Cloud: $131BAnthropic → Nscale: $44.6BAnthropic → Fluidstack: $50BAnthropic → NVIDIA: $10BAnthropic → Riot Platforms: $37.1BAnthropic → Lambda: $34.9BAnthropic → Other providers: $55.6BOpenAI → Amazon Web Services: $188BOpenAI → Microsoft: $250BOpenAI → CoreWeave: $22.4BOpenAI → NVIDIA: $30BOpenAI → Other providers: $20BMicrosoft → Nscale: $43.8BMicrosoft → Nebius: $17.4BMicrosoft → Other providers: $9.7BMeta → CoreWeave: $35.2BMeta → Nebius: $30BUndisclosed buyers → Other providers: $31.1BGoogle Cloud → SpaceXAI: $30.4BFluidstack → Other providers: $25.6BCoreWeave → NVIDIA: $2BCoreWeave → Other providers: $7BNVIDIA → Other providers: $8.28BOther buyers → CoreWeave: $6.51BOther buyers → NVIDIA: $4.5BOther buyers → Riot Platforms: $311MOther buyers → Other providers: $13.9BAnthropic $820BOpenAI $510BMicrosoft $70.9BMeta $65.2BUndisclosed buyers $31.1BGoogle Cloud $30.4BFluidstack $25.6BCoreWeave $9BNVIDIA $8.28BOther buyers $25.2BAmazon Web Services $307BMicrosoft $285BBroadcom $182BSpaceXAI $151BGoogle Cloud $131BNscale $88.4BCoreWeave $64.1BFluidstack $50BNebius $47.4BNVIDIA $46.5BRiot Platforms $37.4BLambda $34.9BOther providers $171B
Confirmed capacity, colocation and supply deals with a disclosed value, summed by buyer and provider. Stated values are contract ceilings in many cases ("up to"), cover different terms, and are not comparable to revenue. Deals without a disclosed value are in the table but not in the diagram.

All deals

Confirmed by a party or a filingReported, not confirmed by a party
Type
Status
TypeTermStatusSource · checked
5 Nov 2026Undisclosed frontier AI labFrontier labIRENNeocloudCapacity contractundisclosed——Confirmed
sec.govExpanded existing contract with Leading Frontier AI Labchecked 10 Nov 2026
4 Nov 2026TeraWulfCapacity landlordGoogle CloudHyperscalerBackstop$19B$19 billion is the value of Anthropic's lease commitments that the Google-supported financing covers; the amount of Google's credit support was not disclosed.401 MW—Confirmed
sec.govdebt financing supporting approximately $19 billion of contracted lease commitments with Anthropic, PBCchecked 9 Nov 2026
4 Nov 2026AnthropicFrontier labRiot PlatformsCapacity landlordColocation lease$28BAbout $28 billion over the 15-year powered-land lease, about $54 billion if both 5-year extensions are exercised; the tenant fits out the 910 MW campus, delivered in phases from September 2027 to July 2028.910 MW15 yrConfirmed
sec.govApproximately $28 billion of total contract value and approximately $1.8 billion of average annual rentchecked 9 Nov 2026
29 Oct 2026NscaleNeocloudNVIDIAChip vendorBackstopNVIDIA Vera Rubinundisclosed460 MW—Reported
thenextweb.comchecked 9 Nov 2026
26 Oct 2026SpaceXAIFrontier labApollo (managed entity)LenderDebt financingNVIDIA Vera Rubin$40BA binding commitment of about $40 billion: an entity managed by Apollo buys GPUs and related servers and leases them to SpaceX for about five years from delivery; closing expected by the end of 2026, with leases starting in the first half of 2027.—5 yrConfirmed
techcrunch.comSpaceX has reached a binding commitment for roughly $40 billion in financing for AI chips and related data center equipment, the company disclosed in a regulatory filing Monday.checked 10 Nov 2026
22 Oct 2026NebiusNeocloudHumainSovereign cloudCapacity contractundisclosed50 MW—Reported
arabnews.comNebius, based in the Netherlands, will off-take up to 50 megawatts from the data center currently under construction.checked 10 Nov 2026
19 Oct 2026AnthropicFrontier labNscaleNeocloudCapacity contractNVIDIA Vera Rubin$45Bamount reportedReported by Bloomberg as talks on a second deal of about $45 billion; not signed.460 MW—Reported
thenextweb.comNscale is negotiating to sell Anthropic about $45bn more in AI computing capacity.checked 9 Nov 2026
12 Oct 2026AnthropicFrontier labIRENNeocloudCapacity contractundisclosed——Reported
cryptobriefing.comAnthropic reportedly signs a multiyear cloud deal with IREN.checked 10 Nov 2026
7 Oct 2026Stonebriar Commercial FinanceEnterpriseABS investorsLenderDebt financing$869Mamount reportedEquipment asset-backed securities in which GPU loans are about 15% of the collateral; pricing was not confirmed.——Reported
thestar.com.myStonebriar Commercial Finance is selling around US$869mil of asset-backed securitieschecked 9 Nov 2026
7 Oct 2026CoreWeaveNeocloudAdaniConneXCapacity landlordColocation leaseNVIDIA Vera Rubinundisclosed240 MW—Confirmed
nasdaq.comThrough a collaboration with AdaniConneX, CoreWeave plans to expand its AI Cloud platform with 240 megawatts (MW) of data center capacity in Navi Mumbai.checked 10 Nov 2026
1 Oct 2026LambdaNeocloudJ.P. Morgan (sole coordinating lead arranger)LenderDebt financing$1.01Bdelayed draw term loan, 6.78% fixed; final maturity May 30 2033—6.7 yrConfirmed
financialcontent.com6.78% fixed interest rate on a semi-annual coupon basischecked 9 Nov 2026
1 Oct 2026Sharon AINeocloudGoldman Sachs and private credit funds (Jarden arranger)LenderDebt financingNVIDIA$356Msenior secured GPU-backed SPV facility, 9.95% fixed (excl. fees)68,000 GPUs—Confirmed
sec.govinaugural US$356m committed senior secured, GPU-backed SPV debt facilitychecked 9 Nov 2026
30 Sep 2026CohereNeolabBoost RunNeocloudCapacity contract$526MDedicated GPU cloud infrastructure for Cohere; about $525.6 million committed over terms of about five years per rack, with initial acceptance expected from the second quarter of 2027 and a refund right if a minimum amount is not accepted by 15 July 2027.—5 yrConfirmed
sec.govCohere has committed to pay Boost Run approximately $525.6 million over the term of the Agreement, a portion of which is payable as a prepaymentchecked 10 Nov 2026
30 Sep 2026VultrNeocloudHPEChip vendorGPU purchaseAMD Helios AI Rack by HPE$1.2BA $1.2 billion order for AMD Helios AI racks built by HPE, to be deployed across Vultr's U.S. cloud data centers; HPE's first order for the platform.——Confirmed
pulse2.comHPE has secured a $1.2 billion order from Vultr to deploy AMD Helios AI Rack by HPE systems across Vultr’s U.S. cloud data centers.checked 10 Nov 2026
29 Sep 2026MetaHyperscalerFirmusNeocloudCapacity contractNVIDIA (DSX platform)undisclosed——Confirmed
channelnewsasia.comAustralia's Firmus said on Tuesday it had signed AI infrastructure agreements with Facebook parent Meta Platforms for graphics processing unit compute capacity at its data centre facilities in Southeast Asiachecked 10 Nov 2026
25 Sep 2026FluidstackNeocloudCipher DigitalCapacity landlordColocation lease$5.2BIncremental revenue from extending the Barber Lake lease to 20 years; total contracted revenue at the site exceeds $9 billion.—10 yrConfirmed
sec.govis expected to generate approximately $5.2 billion of incremental contracted revenue.checked 9 Nov 2026
24 Sep 2026AnthropicFrontier labAkamaiHyperscalerCapacity contractCPU cloud (Akamai Cloud Infrastructure Services)$11.6BSeven-year commitment with potential expansion of up to $9 billion more; Akamai issued Anthropic a warrant for up to about 5% of its stock tied to the expansion.—7 yrConfirmed
sec.govfor $11.6 billion of contractual commitment over seven years.checked 9 Nov 2026
23 Sep 2026Thinking Machines LabNeolabCrusoeNeocloudCapacity contractNVIDIA HGX B200$65MA $65 million annual agreement for Crusoe Managed Inference to serve Thinking Machines Lab models on a dedicated deployment of Nvidia HGX B200 systems; term not disclosed.——Confirmed
crusoe.aitoday announced a $65 million annual agreement to power inference for the lab's open models on Crusoe Cloudchecked 10 Nov 2026
18 Sep 2026CoreWeaveNeocloudBond investors (144A)LenderDebt financing$3.7Bupsized 2.875% convertible senior notes due Apr 1 2033; ~22.5% conversion premium—6.5 yrConfirmed
sec.gov$3.7 billion aggregate principal amount of its 2.875% convertible senior notes due 2033checked 9 Nov 2026
15 Sep 2026NscaleNeocloudNVIDIAChip vendorEquity + compute$1BNvidia committed $1 billion to Nscale's $3.36 billion pre-IPO convertible financing led by Third Point (announced 25 September 2026); the Nvidia tranche is expected to fund in mid-November 2026 and converts into non-voting shares when the IPO completes.——Confirmed
nscale.coman initial $2.36bn tranche at closing and an additional $1bn commitment from NVIDIA with funding expected in mid-November, 2026checked 10 Nov 2026
10 Sep 2026DigitalOceanNeocloudMUFG (agent); Axos, BMO, Wells FargoLenderDebt financingGPU/CPU equipment$725MEquipment finance facility maturing September 2030 with an accordion of up to $300 million. DigitalOcean's Q3 2026 results refer to a $785 million equipment lease facility; the results do not say whether this is the same facility after an increase.—4 yrConfirmed
sec.govit has entered into a new $725 million equipment finance facilitychecked 9 Nov 2026
10 Sep 2026FluidstackNeocloudU.S. DoD Office of Strategic CapitalLenderDebt financing$5Bamount reportedReported by The Wall Street Journal as a loan of about $5 billion under negotiation.——Reported
datacenterdynamics.comchecked 9 Nov 2026
4 Sep 2026AnthropicFrontier labMorgan Stanley (lead), Goldman Sachs, JPMorgan, Citigroup and othersLenderDebt financing$15Bamount reportedReported expansion of Anthropic's revolving credit facility from $2.5 billion; not confirmed as closed.——Reported
theedgemalaysia.comis set to finalise an expansion of its revolving credit facility to US$15 billionchecked 9 Nov 2026
3 Sep 2026Jane StreetEnterpriseCrusoeNeocloudCapacity contract$13Bamount reportedReported by Bloomberg as about $13 billion over five years; neither company confirmed.—5 yrReported
thenextweb.comJane Street is committing roughly $13bn over five years to Crusoechecked 9 Nov 2026
31 Aug 2026AnthropicFrontier labLambdaNeocloudCapacity contractNVIDIA GPUs$34.9BThe August 2026 agreement; Anthropic's agreements with Lambda from May, June and August 2026 total about $41.3 billion into 2034 (registration statement).350 MW6 yrConfirmed
sec.govUnder our August 2026 agreement, which represents approximately $34.9 billion of the aggregate commitment, either party may terminate if Lambda does not timely secure the facility lease.checked 9 Nov 2026
27 Aug 2026LambdaNeocloudMorgan Stanley (lead left arranger); MUFGLenderDebt financing$926Msenior secured term loan B, SOFR+3.00%, issued at 99.5%; matures Dec 31 2030, fully amortizing—4.3 yrConfirmed
lambda.comthe closing of its $926 million senior secured term loan B facilitychecked 9 Nov 2026
27 Aug 2026VoltaNeocloudJPMorgan and Goldman Sachs (arrangers)LenderDebt financing$5Bamount reportedA US$5 billion leveraged loan for Volta's data center complex in Norway, arranged by JPMorgan and Goldman Sachs; reported sold to investors in mid-October 2026 at 6.5 percentage points over the benchmark rate and 95 cents on the dollar (reported, not confirmed).——Reported
businesstimes.com.sgJPMORGAN Chase and Goldman Sachs Group hiked the yield and sweetened terms on a US$5 billion leveraged loan sale for Volta Infrastructure Holdingschecked 10 Nov 2026
26 Aug 2026AnthropicFrontier labNscaleNeocloudCapacity contractNVIDIA (Vera Rubin per media)$44.6BUp to about $44.6 billion into 2033; fees accrue only as capacity is delivered and accepted.460 MW—Confirmed
sec.govwe agreed to spend an aggregate of up to approximately $44.6 billion over terms extending into 2033, with fees accruing only as capacity is delivered to and accepted by us.checked 9 Nov 2026
21 Aug 2026BroadcomChip vendorLenders incl. Blackstone, Apollo (in talks)LenderDebt financingBroadcom custom XPUs for Anthropic and others$60Bamount reportedReported by Bloomberg as more than $60 billion sought from lenders; talks.——Reported
thenextweb.comBroadcom is in talks with lenders to raise more than $60bn in debtchecked 9 Nov 2026
17 Aug 2026OpenAIFrontier labSB EnergyCapacity landlordColocation leaseNVIDIA (exclusively hosts NVIDIA AI compute)undisclosed8 GW20 yrConfirmed
sec.govSB Energy will build, own and operate the data center under a 20-year lease to OpenAI.checked 9 Nov 2026
17 Aug 2026SB EnergyCapacity landlordNVIDIAChip vendorBackstop$105BCap on Nvidia's guarantees of land, power and shell payments for OpenAI's leases at the PORTS campus in Ohio, expected to decline over each phase's 20-year lease.4.25 GW20 yrConfirmed
sec.govIn August 2026, we entered into guarantees, capped at a total of $105 billion, to provide credit supportchecked 9 Nov 2026
17 Aug 2026SB EnergyCapacity landlordNVIDIAChip vendorEquity + compute$1.5BNvidia equity investment in SB Energy——Confirmed
sec.govNVIDIA will invest $1.5 billion in SB Energy, joining existing investors SoftBank Group and OpenAI.checked 9 Nov 2026
10 Aug 2026CoreWeaveNeocloudJPMorgan, MUFG (joint lead arrangers)LenderDebt financing$2.6Bdelayed draw term loan; SOFR+5.50%; ~5-year maturity—5 yrConfirmed
sec.govtoday announced it has closed its $2.6 billion delayed draw term loan facilitychecked 9 Nov 2026
10 Aug 2026AnthropicFrontier labRiot PlatformsCapacity landlordColocation lease$9.1BTotal initial contract revenue for 191 MW at Rockdale; about $16.1 billion if both extensions are exercised.191 MW20 yrConfirmed
sec.govexpected to generate approximately $9.1 billion in total initial contract revenuechecked 9 Nov 2026
4 Aug 2026AnthropicFrontier labVoltaNeocloudCapacity contractNVIDIA Vera Rubin$10Bamount reportedVolta announced a $10 billion, six-year contract with an unnamed AI lab; Bloomberg reported that the customer is Anthropic.133 MW6 yrReported
thestar.com.mychecked 9 Nov 2026
4 Aug 2026VoltaNeocloudBitdeerCapacity landlordColocation leaseNVIDIA Rubin$4.7BContracted revenue over the 16-year base term; an 8-year renewal option would take it to about $8.0 billion.121 MW16 yrConfirmed
finviz.comThe agreement represents approximately $4.7 billion in contracted revenue over the initial 16-year base term.checked 9 Nov 2026
30 Jul 2026Nexus Data Centers (Anthropic Hubbard TX campus)Capacity landlordGoogle CloudHyperscalerBackstopundisclosed1.6 GW—Reported
thestar.com.myIn return for its support, Google is expected to receive an equity stake of about 20% in the data-center and power project.checked 9 Nov 2026
30 Jul 2026Nexus Data CentersCapacity landlordMorgan Stanley-led bank groupLenderDebt financingGoogle/Broadcom TPU (per reports)$15Bamount reportedReported as advanced talks on a $14 billion bridge loan and a revolving credit facility; not closed.1.6 GW—Reported
thestar.com.myNexus Data Centers is in advanced talks to raise $15 billionchecked 9 Nov 2026
28 Jul 2026AMDChip vendorCore ScientificCapacity landlordColocation leaseundisclosed500 MW—Confirmed
sec.govAMD to secure up to 2.5 gigawatts of data center capacity to support end customer deployments of AMD AI solutions.checked 9 Nov 2026
28 Jul 2026Galaxy Digital (Galaxy Helios Data Centers II LLC)Capacity landlordBond investors (144A)LenderDebt financing$3.51B9.875% senior secured notes due Aug 1 2031260 MW5 yrConfirmed
sec.govThe aggregate principal amount of Notes sold in the Offering was $3,507,000,000.checked 9 Nov 2026
20 Jul 2026Undisclosed (Beacon Point Phase 1 tenant)UndisclosedHut 8Capacity landlordColocation lease$9.8BPhase 2 of Beacon Point; together with Phase 1 the tenant leases 704 MW for about $19.6 billion.352 MW15 yrConfirmed
sec.gov$9.8 billion over a 15-year base lease termchecked 9 Nov 2026
17 Jul 2026NebiusNeocloudMUFG (structuring agent); ABN AMRO, Bank of America, Deutsche Bank, HSBC (MLAs)LenderDebt financing$775Mfirst senior secured GPU-backed facility; SOFR+2.50%; matures Oct 31 2030—4.3 yrConfirmed
sec.goventered into its first senior secured debt facility for approximately $775 million.checked 9 Nov 2026
16 Jul 2026Undisclosed global AI labUndisclosedSharonAINeocloudCapacity contract$1.32Bover five years—5 yrConfirmed
sec.govvalued at US$1.32 billion over five yearschecked 9 Nov 2026
6 Jul 2026AnthropicFrontier labTeraWulfCapacity landlordColocation lease$19BApproximate contracted revenue over the initial 20-year lease; Google provides credit support for the project financing.401 MW20 yrConfirmed
sec.govThe lease is expected to generate approximately $19 billion of contracted revenue over the initial lease term.checked 9 Nov 2026
1 Jul 2026AnthropicFrontier labAMDChip vendorChip supplyAMD Helios rack-scale, Instinct MI450$20BExpected spend above $20 billion if the full initial capacity is procured; there is no fixed dollar commitment, and an option covers additional capacity.——Confirmed
sec.govIf we procure the full amount of this initial committed capacity, we expect aggregate expenditures to exceed $20.0 billion over the term of the agreementchecked 9 Nov 2026
1 Jul 2026AnthropicFrontier labAMDChip vendorEquity + computeAMD Instinct MI450$5BUp to $5 billion of Anthropic stock that AMD commits to buy in increments as GPU delivery milestones are met, the first expected in 2027.——Confirmed
sec.govhas provided a commitment to purchase up to $5.0 billion of our Class N common stock, which becomes available for us to draw on in incrementschecked 9 Nov 2026
22 Jun 2026Reflection AINeolabSpaceXAINeocloudCapacity contractNVIDIA GB300$6.3Bamount reportedper CNBC: $150M/month from Jul 1 2026 through 2029 (~$6.3B if full term); 90-day exit after first three months—3 yrConfirmed
thestar.com.myagreed to pay SpaceX $150 million per month beginning July 1, 2026, through 2029checked 9 Nov 2026
18 Jun 2026CoreWeaveNeocloudBond investors (144A)LenderDebt financing$1.25BUS dollar tranche only ($1.25 billion of 9.625% notes due 2032); CoreWeave issued EUR 2.0 billion of 8.500% notes due 2032 at the same time.—6 yrConfirmed
sec.gov€2,000 million in aggregate principal amount of its euro-denominated 8.500% Senior Notes due 2032checked 9 Nov 2026
9 Jun 2026Applied Digital (APLD ComputeCo 3 LLC)Capacity landlordBond investors (144A)LenderDebt financing$1.59B7.000% senior secured notes due 2031150 MW5 yrConfirmed
sec.govhas priced a $1.59 billion offering (the “Offering”)checked 9 Nov 2026
9 Jun 2026Broadcom AI XPV PlatformChip vendorApollo (lead); Blackstone Credit & InsuranceLenderDebt financingBroadcom custom XPUs (incl. Google TPU racks)$35BInitial $35 billion tranche of a financing platform that targets more than 20 GW of AI compute through 2028.20 GW—Confirmed
convergedigest.comThe platform initiates operations with a massive $35 billion tranche led by Apollochecked 9 Nov 2026
8 Jun 2026Cipher Digital (Stingray Compute LLC)Capacity landlordBond investors (144A)LenderDebt financing$810M6.000% senior secured notes due 2031—5 yrConfirmed
sec.govpriced a $810.0 million offering of 6.000% senior secured notes due 2031checked 9 Nov 2026
8 Jun 2026NVIDIAChip vendorSharonAINeocloudCapacity contractNVIDIA GB300$4.88BUp to $4.88 billion; GPU clusters are delivered in phases.72 MW6 yrConfirmed
sec.govwhich has a contract value of up to $4.88 billionchecked 9 Nov 2026
8 Jun 2026Undisclosed tier-one investment-grade hyperscalerHyperscalerApplied DigitalCapacity landlordColocation lease$5.2BA 210 MW, 15-year lease at the Delta Forge 2 campus in Alabama with an unnamed tier-one investment-grade hyperscaler, about $5.2 billion of base-term contracted revenue.210 MW15 yrConfirmed
sec.govsigned a 210 MW, 15-year lease at Delta Forge 2 with the Company’s tier-one investment grade hyperscaler customer, representing approximately $5.2 billion of base-term contracted revenuechecked 10 Nov 2026
5 Jun 2026Google CloudHyperscalerSpaceXAINeocloudCapacity contractNVIDIA GPUs$30.4BCalculated from $920 million a month from October 2026 to June 2029; either party may terminate on 90 days' notice after 31 December 2026.110,000 GPUs2.75 yrConfirmed
sec.govthe customer has agreed to pay us $920 million per month from October 2026 through June 2029checked 9 Nov 2026
4 Jun 2026Hut 8 (Beacon Point DC LLC)Capacity landlordInvestment-grade bond investors (144A private offering)LenderDebt financing$4.25B6.129% senior secured notes due Nov 30 2042, fully amortizing from May 2030; non-recourse to Hut 8352 MW16.5 yrConfirmed
sec.govThe Notes will bear interest at a rate of 6.129% per annumchecked 9 Nov 2026
29 May 2026IREN (Hardware 3)NeocloudGoldman Sachs, JPMorgan (joint lead arrangers)LenderDebt financingNVIDIA GB300$3.6B~$1.5B DDTL at SOFR+2.25% + $2.1B 5.96% senior notes, both due Dec 31 2031; IREN PR calls it $3.65bn, Fitch A / DBRS A(low)—5.5 yrConfirmed
sec.govfor an aggregate financing of approximately $3.6 billionchecked 9 Nov 2026
21 May 2026Thinking Machines LabNeolabBoost RunNeocloudCapacity contractNVIDIA B300$472MCombined value of two order forms over an initial 36-month term.5,000 GPUs3 yrConfirmed
sec.govfor an initial term of 36 months, with a combined total contract value of approximately $471.7 millionchecked 9 Nov 2026
19 May 2026Google-Blackstone TPU cloud JVNeocloudGoogle CloudHyperscalerJoint ventureGoogle TPU$5BBlackstone's initial equity commitment as majority owner of a TPU cloud joint venture with Google; the first 500 MW is expected online in 2027.500 MW—Confirmed
ciodive.comBlackstone will make an initial commitment of $5 billion in equity capitalchecked 9 Nov 2026
18 May 2026CoreWeaveNeocloudMorgan Stanley, MUFG (joint lead arrangers)LenderDebt financing$3.1BDDTL 5.0; SOFR+4.50%; ~5.5-year maturity—5.5 yrConfirmed
sec.govit has closed its $3.1 billion delayed draw term loan facilitychecked 9 Nov 2026
12 May 2026IRENNeocloudConvertible note investors (144A)LenderDebt financing$2.6B1.00% convertible senior notes due December 2033; the initial purchasers had an option for up to $400 million more.—7.5 yrConfirmed
sec.govoffering of $2.6 billion aggregate principal amount of 1.00% convertible senior notes due 2033checked 9 Nov 2026
7 May 2026NVIDIAChip vendorIRENNeocloudCapacity contractNVIDIA Blackwell (air-cooled)$3.4BFive-year managed AI cloud contract; IREN also granted Nvidia the right to buy up to 30 million shares at $70.60 MW5 yrConfirmed
sec.govWe also signed a 5-year, $3.4bn AI Cloud contract with NVIDIA and entered into a broader strategic partnershipchecked 9 Nov 2026
6 May 2026Undisclosed high-investment-grade tenant (Beacon Point Phase 1)UndisclosedHut 8Capacity landlordColocation lease$9.8BPhase 1 of Beacon Point; the tenant is rated AA- or higher and also signed Phase 2 in July 2026.352 MW15 yrConfirmed
sec.govrepresenting $9.8 billion in base-term contract value on a triple-net, take-or-pay basischecked 9 Nov 2026
3 May 2026AnthropicFrontier labSpaceXAI (SpaceX; formerly xAI)NeocloudCapacity contractNVIDIA GPUs (Colossus, Colossus II)$121BUp to $120.5 billion into 2029, about $3.1 billion a month once all capacity is delivered; after the initial non-cancellable periods either side may end the arrangements on 90 days' notice.325,000 GPUs3 yrConfirmed
sec.govwe agreed to spend an aggregate of up to $120.5 billion over terms extending into 2029, consisting of approximately $3.1 billion in the aggregate per month once all capacity has been deliveredchecked 9 Nov 2026
30 Apr 2026Hut 8 (Hut 8 DC LLC)Capacity landlordInvestment-grade bond investors (144A private offering)LenderDebt financing$3.25B6.192% senior secured notes due 2042; fully amortizing 16.5-year (per Q1 2026 release)245 MW16.5 yrConfirmed
sec.gov6.192% Senior Secured Notes due 2042checked 9 Nov 2026
24 Apr 2026SpaceXAIFrontier labValor Equity PartnersLenderDebt financingNVIDIA$6.59BTotal undiscounted payments under a five-year equipment lease of AI infrastructure hardware.—5 yrConfirmed
sec.govfor certain AI infrastructure hardware (“Valor transaction III”) for total undiscounted lease payments of $6,587 million.checked 9 Nov 2026
23 Apr 2026Thinking Machines LabNeolabGoogle CloudHyperscalerCapacity contractNVIDIA GB300 (A4X Max)undisclosed——Confirmed
eweek.comsources familiar with the deal told TechCrunch the agreement is valued in the “single-digit billions.”checked 10 Nov 2026
20 Apr 2026AnthropicFrontier labAmazon Web ServicesHyperscalerCapacity contractTrainium2-Trainium4, Graviton$110BMinimum spend from May 2026 to April 2036 (registration statement); Anthropic's announcement cited more than $100 billion over ten years and up to 5 GW.5 GW10 yrConfirmed
sec.govwe committed to spend an aggregate of at least $110.0 billion between May 2026 and April 2036, regardless of actual usage.checked 9 Nov 2026
20 Apr 2026AnthropicFrontier labAmazon Web ServicesHyperscalerEquity + compute$5BAbout $5.0 billion of preferred stock, plus up to $20.0 billion of further financing available in $5 billion increments as compute milestones are met (registration statement).——Confirmed
sec.govAmazon purchased 19.3 million shares of the Company’s Series G-2 non-voting redeemable convertible preferred stock for approximately $5.0 billion and will provide up to $20.0 billion of debt and/or equity financing in…checked 9 Nov 2026
15 Apr 2026Jane StreetEnterpriseCoreWeaveNeocloudEquity + computeNVIDIA Vera Rubin$6BAbout $6 billion of commitments to use CoreWeave's AI cloud; Jane Street also invested $1 billion in CoreWeave stock at $109 a share.——Confirmed
coreweave.comJane Street has committed approximately $6 billion to use CoreWeave’s AI cloud platform.checked 9 Nov 2026
14 Apr 2026CoreWeaveNeocloudBond investors (144A)LenderDebt financing$5.75B$1.75B 9.750% senior notes due Oct 1 2031 + $4.0B 1.75% convertible senior notes due Oct 1 2032 (closed same day)—5.5 yrConfirmed
sec.gov$4,000,000,000 aggregate principal amount of its 1.75% Convertible Senior Notes due 2032checked 9 Nov 2026
10 Apr 2026AnthropicFrontier labCoreWeaveNeocloudCapacity contractundisclosed——Confirmed
coreweave.comchecked 9 Nov 2026
6 Apr 2026AnthropicFrontier labBroadcomChip vendorChip supplyGoogle TPU (custom, Broadcom-built), leased as racks$161BAbout $161.2 billion of aggregate rent, excluding interest, over five-year TPU equipment leases (registration statement); access to about 3.5 GW of TPU compute from 2027 depends on Anthropic's commercial success (Broadcom current report).3.5 GW5 yrConfirmed
sec.govOur rent payments over the life of these leases are equal to an aggregate of approximately $161.2 billion excluding interestchecked 9 Nov 2026
6 Apr 2026AnthropicFrontier labGoogle CloudHyperscalerCapacity contractGoogle TPU (incl. TPUs supplied through Broadcom)$121BMinimum spend from April 2026 to July 2033 under a hosting agreement amended between May and October 2026 (registration statement).—7 yrConfirmed
sec.govpursuant to which we committed to spend at least approximately $121.3 billion between April 2026 and July 2033, regardless of actual usage.checked 9 Nov 2026
31 Mar 2026AnthropicFrontier labBroadcomChip vendorDebt financingGoogle TPU (Broadcom-supplied)$42BUp to $42 billion of convertible notes that Anthropic may issue to Broadcom solely to finance rent under its TPU equipment leases.—5 yrConfirmed
sec.govwe have the ability to issue, if needed, up to $42.0 billion in aggregate principal amount of convertible promissory notes to Broadcomchecked 9 Nov 2026
31 Mar 2026CoreWeaveNeocloudBlackstone Credit & Insurance (anchor); MUFG, Morgan Stanley (structuring)LenderDebt financing$8.5BAbout $7.5 billion is drawable at first, rising to $8.5 billion as assets stabilize; matures in March 2032.—6 yrConfirmed
sec.govit has closed an $8.5 billion delayed draw term loan facilitychecked 9 Nov 2026
30 Mar 2026Mistral AINeolabBank consortium (BNP Paribas, Credit Agricole CIB, HSBC, MUFG + 3 others)LenderDebt financingNVIDIA GB300$830MMistral's first debt raise; to buy 13,800 Nvidia chips (GB300 per media)44 MW—Confirmed
finance.yahoo.comraised $830 million in new debt to buy 13,800checked 9 Nov 2026
16 Mar 2026MetaFrontier labNebiusNeocloudCapacity contractNVIDIA Vera Rubin$27BUp to about $27 billion: $12 billion of dedicated capacity plus Meta's commitment to buy up to $15 billion of additional capacity over five years.—5 yrConfirmed
sec.govThe agreement has a contract value of up to approximately $27 billion.checked 9 Nov 2026
11 Mar 2026NebiusNeocloudNVIDIAChip vendorEquity + computeNVIDIA Rubin, Vera CPUs, BlueField$2Bequity investment (structure not in release; media: pre-funded warrants for ~21M shares)5 GW—Confirmed
sec.govNVIDIA will invest $2 billion in Nebiuschecked 9 Nov 2026
10 Mar 2026Thinking Machines LabNeolabNVIDIAChip vendorEquity + computeNVIDIA Vera Rubinundisclosed1 GW—Confirmed
techcrunch.comdeploying at least one gigawatt of Nvidia’s Vera Rubin systemschecked 9 Nov 2026
4 Mar 2026Applied Digital (APLD ComputeCo 2 LLC)Capacity landlordBond investors (144A)LenderDebt financing$2.15B6.750% senior secured notes due 2031, issued at 98%200 MW5 yrConfirmed
sec.govhas priced a $2.15 billion offeringchecked 9 Nov 2026
1 Mar 2026AnthropicFrontier labGoogle CloudHyperscalerEquity + compute$10BAbout $10 billion of preferred stock, plus Google's commitment to provide further debt or equity financing through 2030 (registration statement).——Confirmed
sec.govGoogle purchased 38.6 million shares of the Company’s Series G-2 non-voting redeemable convertible preferred stock for approximately $10.0 billion and will provide up to $30.0 billion of debt and/or equity financing t…checked 9 Nov 2026
1 Mar 2026Amazon Web ServicesHyperscalerCerebrasChip vendorChip supplyCerebras wafer-scale systems in AWS data centersundisclosed——Reported
sec.govto acquire up to 2,696,678 shares of Class N common stockchecked 9 Nov 2026
1 Mar 2026MetaFrontier labCoreWeaveNeocloudCapacity contract$21BNew commitment signed in March 2026, in addition to the September 2025 agreement.——Confirmed
sec.govExecuted multiple new agreements with Meta, including a new $21 billion commitment signed in March.checked 9 Nov 2026
27 Feb 2026OpenAIFrontier labAmazon Web ServicesHyperscalerEquity + compute$50B$15 billion invested initially and $35 billion when conditions are met; announced with a $100 billion expansion of OpenAI's AWS contract.——Confirmed
sec.govAmazon will also invest $50 billion in OpenAIchecked 9 Nov 2026
27 Feb 2026OpenAIFrontier labAmazon Web ServicesHyperscalerCapacity contractTrainium3, Trainium4$100Bexpansion of the existing $38B agreement by $100B over 8 years2 GW8 yrConfirmed
sec.govOpenAI and AWS are expanding their existing $38 billion multi-year agreement by $100 billion over 8 years.checked 9 Nov 2026
27 Feb 2026OpenAIFrontier labNVIDIAChip vendorEquity + computeNVIDIA Vera Rubin$30BNvidia equity investment in OpenAI's $110B round (later $122B, closed Mar 31 2026); compute = 3 GW dedicated inference + 2 GW training on Vera Rubin5 GW—Confirmed
cnbc.comOpenAI will use 3 gigawatts of dedicated inference capacity and 2 gigawatts of training capacitychecked 9 Nov 2026
26 Feb 2026MetaFrontier labGoogle CloudHyperscalerCapacity contractGoogle TPUundisclosed——Reported
thestar.com.mya multi-billion dollar deal to rent artificial intelligence chips from Googlechecked 9 Nov 2026
24 Feb 2026MetaFrontier labAMDChip vendorChip supplycustom AMD Instinct (MI450 architecture), EPYC Venice, Helios rackundisclosed6 GW—Confirmed
sec.govAMD has issued Meta a performance-based warrant for up to 160 million shares of AMD common stockchecked 9 Nov 2026
18 Feb 2026MetaFrontier labNVIDIAChip vendorGPU purchaseBlackwell, Rubin GPUs; Grace CPUs (standalone); Vera CPUs from 2027; Spectrum-Xundisclosed——Confirmed
pureai.comNVIDIA said it will supply Meta with millions of Blackwell and Rubin GPUschecked 9 Nov 2026
11 Feb 2026Mistral AINeolabEcoDataCenterCapacity landlordColocation leaseNVIDIA Vera Rubin$1.4BEUR 1.2B investment (USD ~1.4B per media conversion)——Confirmed
ecodatacenter.techa strategic, long-term investment of €1.2 billion in Sweden’s digital infrastructurechecked 9 Nov 2026
26 Jan 2026CoreWeaveNeocloudNVIDIAChip vendorEquity + compute$2BClass A common stock investment; closed in Q1 20265 GW—Confirmed
sec.govClosed $2 billion Class A common stock investment from NVIDIA.checked 9 Nov 2026
16 Jan 2026AMDChip vendorRiot PlatformsCapacity landlordColocation lease$311MInitial 10-year term; three 5-year extensions would bring about $1.0 billion, and AMD holds options on up to 200 MW.25 MW10 yrConfirmed
sec.govis expected to generate approximately $311.0 million in contract revenue.checked 9 Nov 2026
14 Jan 2026CerebrasChip vendorOpenAILenderDebt financing$1Bsecured promissory note ('Working Capital Loan') funded by OpenAI in January 2026, 6% stated interest; repaid via non-cash billings ($918.2M outstanding at Jun 30 2026)——Confirmed
sec.gova secured promissory note of approximately $1.0 billion (the “Working Capital Loan”) funded by OpenAI in January 2026checked 9 Nov 2026
14 Jan 2026OpenAIFrontier labCerebrasChip vendorCapacity contractCerebras WSE-3 (wafer-scale inference)$20BMore than $20 billion per Cerebras's registration statement for 750 MW, with an option on 1.25 GW more; January 2026 media reports cited more than $10 billion.750 MW—Confirmed
sec.govIn January 2026, we announced a multi-year deal with OpenAI valued at more than $20 billion dollars.checked 9 Nov 2026
1 Jan 2026xAI (CTC subsidiary)Frontier labValor Equity PartnersLenderDebt financingNVIDIA$5.37Bdebt recorded for 'Valor transaction II' GPU equipment lease (failed sale-leaseback); entered Jan 2026, amended Feb 18 2026——Confirmed
sec.govThe Valor transaction II is deemed to be a failed sale-leaseback transaction and the Company recorded the related debt of $5,365 millionchecked 9 Nov 2026
17 Dec 2025AnthropicFrontier labHut 8Capacity landlordColocation leaseundisclosed245 MW—Confirmed
canada.hut8.comat least 245 megawatts (MW) and up to 2,295 MW of AI data center infrastructurechecked 9 Nov 2026
17 Dec 2025FluidstackNeocloudHut 8Capacity landlordColocation lease$7BTotal over the 15-year base term; Google backstops the lease and Fluidstack holds a right of first offer on up to 1,000 MW more.245 MW15 yrConfirmed
sec.govTotal contract value of $7.0 billion over a 15-year base lease termchecked 9 Nov 2026
17 Dec 2025Hut 8Capacity landlordGoogle CloudHyperscalerBackstopundisclosed245 MW15 yrConfirmed
sec.govGoogle providing a financial backstop covering obligations for the 15-year base lease termchecked 9 Nov 2026
11 Dec 2025AnthropicFrontier labBroadcomChip vendorChip supplyGoogle TPU Ironwood racks$21B$10B order (disclosed Sep 2025, customer unnamed) + $11B additional order in Broadcom's FQ4 2025——Confirmed
trendforce.comordered the latest TPU Ironwood racks and added another $11 billion orderchecked 9 Nov 2026
8 Dec 2025IRENNeocloudConvertible note investors (144A)LenderDebt financing$2.3B$1.15B 0.25% converts due 2032 + $1.15B 1.00% converts due 2033; partly used to repurchase 2029/2030 converts——Confirmed
sec.govIREN closed its offering of $1.15 billion aggregate principal amount of 0.25% convertible senior notes due 2032checked 9 Nov 2026
19 Nov 2025HUMAINSovereignAMD, CiscoChip vendorJoint ventureAMD Instinct MI450undisclosed1 GW—Confirmed
thestar.com.myThe plans include building up to one gigawatt of new data centers to support the joint venture by 2030.checked 9 Nov 2026
19 Nov 2025HUMAINSovereignAmazon Web ServicesHyperscalerJoint ventureNVIDIA GB300, AWS Trainium$5BMore than $5 billion of AWS investment committed in May 2025; the value of the November 2025 expansion was not disclosed.150,000 GPUs—Confirmed
press.aboutamazon.complans to provide, deploy and manage up to 150,000 AI acceleratorschecked 9 Nov 2026
19 Nov 2025SpaceXAIFrontier labHUMAINSovereign cloudCapacity contractNVIDIAundisclosed500 MW—Reported
nbcnews.comthe 500-megawatt data center for xAI would be powered by Nvidia's computing chipschecked 9 Nov 2026
18 Nov 2025AnthropicFrontier labMicrosoftHyperscalerCapacity contractNVIDIA$30BAnnounced as a $30 billion commitment; after amendments Anthropic reports at least $44.9 billion for November 2026 to June 2033 (registration statement).1 GW—Confirmed
blogs.microsoft.comAnthropic has committed to purchase $30 billion of Azure compute capacitychecked 9 Nov 2026
18 Nov 2025AnthropicFrontier labMicrosoftHyperscalerEquity + compute$5BMicrosoft committed to invest up to $5 billion; Nvidia committed up to $10 billion at the same time.——Confirmed
blogs.microsoft.comNVIDIA and Microsoft are committing to invest up to $10 billion and up to $5 billion respectively in Anthropic.checked 9 Nov 2026
18 Nov 2025AnthropicFrontier labNVIDIAChip vendorEquity + computeNVIDIA$10BUp to $10 billion investment commitment announced together with the Microsoft agreement.1 GW—Confirmed
blogs.microsoft.comNVIDIA and Microsoft are committing to invest up to $10 billion and up to $5 billion respectively in Anthropic.checked 9 Nov 2026
13 Nov 2025Applied Digital (APLD ComputeCo LLC)Capacity landlordHigh-yield bond investors (144A)LenderDebt financing$2.35B9.250% senior secured notes due 2030, issued at 97%—5 yrConfirmed
sec.govpriced its offering of $2.35 billion aggregate principal amount of 9.250% senior secured notes due 2030checked 9 Nov 2026
12 Nov 2025AnthropicFrontier labFluidstackNeocloudColocation lease$50BAnthropic's announced investment in US computing infrastructure (data centers built with Fluidstack in TX and NY)——Confirmed
anthropic.comwe are announcing a $50 billion investment in American computing infrastructurechecked 9 Nov 2026
11 Nov 2025MetaFrontier labNebiusNeocloudCapacity contract$3Bapprox. value over 5 years—5 yrConfirmed
sec.gova new agreement to deliver AI infrastructure to Meta valued at approximately $3 billion over 5 years.checked 9 Nov 2026
5 Nov 2025Cipher Mining (Cipher Compute LLC)Capacity landlordHigh-yield bond investors (144A)LenderDebt financing$1.4B7.125% senior secured notes due 2030 at par; $333M add-on (Nov 24 2025) took the series to $1.733B168 MW5 yrConfirmed
sec.govThe Issuer intends to use the net proceeds from the Offering to finance a portion of the construction cost of the Barber Lake Facilitychecked 9 Nov 2026
3 Nov 2025Amazon Web ServicesHyperscalerCipher DigitalCapacity landlordColocation lease$5.5Bapprox. contract value over 15 years300 MW15 yrConfirmed
sec.govCipher today announced an approximately $5.5 billion, 15-year lease agreement with Amazon Web Serviceschecked 9 Nov 2026
3 Nov 2025MicrosoftHyperscalerIRENNeocloudCapacity contractNVIDIA GB300$9.7BTotal value over five years, including a 20% prepayment.200 MW5 yrConfirmed
sec.govwith a total contract value of approximately $9.7 billionchecked 9 Nov 2026
3 Nov 2025MicrosoftHyperscalerLambdaNeocloudCapacity contractNVIDIA GB300 NVL72undisclosed——Confirmed
lambda.comLambda, the Superintelligence Cloud, today announced a multibillion-dollar agreement with Microsoft to deploy AIchecked 9 Nov 2026
3 Nov 2025OpenAIFrontier labAmazon Web ServicesHyperscalerCapacity contractNVIDIA GB200, GB300 (EC2 UltraServers)$38Bmulti-year, growing over seven years—7 yrConfirmed
aboutamazon.comUnder this new $38 billion agreement, which will have continued growth over the next seven years,checked 9 Nov 2026
30 Oct 2025PoolsideNeolabNVIDIAChip vendorEquity + computeNVIDIA GB300$1Bamount reportedReported by Bloomberg: Nvidia's investment would start at $500 million and rise to $1 billion if Poolside meets fundraising targets.——Reported
bloomberg.comchecked 9 Nov 2026
29 Oct 2025AnthropicFrontier labAmazon Web ServicesHyperscalerCapacity contractAWS Trainium2undisclosed500,000 GPUs—Confirmed
aboutamazon.comwhich features nearly half a million Trainium2 chips and provides more than five times the compute powerchecked 9 Nov 2026
28 Oct 2025FluidstackNeocloudTeraWulf (Abernathy JV)Capacity landlordJoint venture$9.5Bcontracted revenue to the JV over 25-year hosting commitment (may be shortened to 20 or 15 years)168 MW25 yrConfirmed
sec.govThe 25-year hosting commitment represents approximately $9.5 billion in contracted revenue to the joint venture.checked 9 Nov 2026
28 Oct 2025OpenAIFrontier labMicrosoftHyperscalerCapacity contract$250Bincremental Azure services commitment (no term disclosed)——Confirmed
blogs.microsoft.comOpenAI has contracted to purchase an incremental $250B of Azure serviceschecked 9 Nov 2026
28 Oct 2025TeraWulf (Abernathy JV)Capacity landlordGoogle CloudHyperscalerBackstop$1.3BGoogle backstops $1.3 billion of Fluidstack's long-term lease obligations supporting project debt at the Abernathy joint venture.168 MW—Confirmed
sec.govGoogle backstops $1.3 billion of Fluidstack's long-term lease obligations in support of project debtchecked 9 Nov 2026
23 Oct 2025AnthropicFrontier labGoogle CloudHyperscalerCapacity contractGoogle TPU (up to 1M TPUs)undisclosed1 GW—Confirmed
anthropic.combring well over a gigawatt of capacity online in 2026checked 9 Nov 2026
22 Oct 2025Undisclosed U.S. investment-grade hyperscalerHyperscalerApplied DigitalCapacity landlordColocation lease$5Bapprox. prospective lease revenue over ~15-year term200 MW15 yrConfirmed
sec.govrepresenting approximately $5 billion of prospective lease revenue over the term of its leasechecked 9 Nov 2026
21 Oct 2025MetaFrontier labBlue Owl Capital (funds)LenderJoint venture$27BAbout $27 billion of total development costs for the Hyperion campus, funded 80% by Blue Owl and 20% by Meta.—4 yrConfirmed
investor.atmeta.comapproximately $27 billion in total development costs.checked 9 Nov 2026
20 Oct 2025Vantage Data Centers (Frontier, Shackelford County TX; Port Washington WI)Capacity landlordJPMorgan, MUFG (lead banks)LenderDebt financing$38Bamount reportedReported financing of two facilities ($23.25 billion in Texas and $14.75 billion in Wisconsin); closing was not confirmed.——Reported
itiger.comchecked 9 Nov 2026
16 Oct 2025TeraWulf (WULF Compute LLC)Capacity landlordMorgan Stanley (sole bookrunner); 144A investorsLenderDebt financing$3.2B7.750% senior secured notes due Oct 15 2030, at par—5 yrConfirmed
sec.govhas priced a $3.2 billion offering (the “Offering”) of 7.750% senior secured notes due 2030 (the “Notes”) at par.checked 9 Nov 2026
15 Oct 2025MicrosoftHyperscalerNscaleNeocloudCapacity contractNVIDIA GB300; later Vera Rubin NVL72 (66,000+ at Sines)$43.8BUp to about $43.8 billion through December 2033 under statements of work signed between September 2025 and April 2026; in October 2026 Microsoft withdrew from the 50 MW Loughton, UK site. In November 2026 the Financial Times reported that Microsoft had declined an option to more than double the capacity it rents at Nscale's 240 MW Barstow, Texas campus; the existing Texas contract stays in place (reported, not confirmed).200,000 GPUs—Confirmed
sec.govprovide for payments to us of up to approximately $43.8 billion through December 2033checked 10 Nov 2026
15 Oct 2025PoolsideNeolabCoreWeaveNeocloudCapacity contractNVIDIA GB300 NVL72undisclosed250 MW—Confirmed
investors.coreweave.comCoreWeave will provide a state-of-the-art cluster of NVIDIA GB300 NVL72 systems, including more than 40,000 GPUs.checked 9 Nov 2026
14 Oct 2025OracleHyperscalerAMDChip vendorGPU purchaseAMD Instinct MI450 (Helios racks)undisclosed50,000 GPUs—Confirmed
newsroom.amd.compowered by 50,000 AMD Instinct MI450 Series GPUs.checked 9 Nov 2026
13 Oct 2025OpenAIFrontier labBroadcomChip vendorChip supplyOpenAI-designed custom accelerator (first chip 'Jalapeno' unveiled Jun 24 2026) + Broadcom Ethernet racksundisclosed10 GW—Confirmed
cnbc.comjointly building and deploying 10 gigawatts of custom artificial intelligence acceleratorschecked 9 Nov 2026
12 Oct 2025xAI (CTC subsidiary)Frontier labValor Equity PartnersLenderDebt financingNVIDIA (Colossus 2)$4.51BThe value is the debt recorded at 31 December 2025 for a GPU equipment lease accounted for as financing; the full vehicle was reported at about $20 billion.—5 yrConfirmed
sec.govthe Company recorded the related debt of $455 million and $4,052 million within Debt and finance leases, current and Debt and finance leases, net of currentchecked 9 Nov 2026
6 Oct 2025OpenAIFrontier labAMDChip vendorGPU purchaseAMD Instinct MI450 (first 1 GW from 2H 2026)undisclosed6 GW—Confirmed
sec.govAMD has issued OpenAI a warrant for up to 160 million shares of AMD common stock, structured to vest as specific milestones are achieved.checked 9 Nov 2026
1 Oct 2025OpenAIFrontier labSamsung Electronics; SK hynixChip vendorChip supplyDRAM / HBMundisclosed——Reported
techcrunch.comproduce up to 900,000 high-bandwidth DRAM memory chips per monthchecked 9 Nov 2026
25 Sep 2025Cipher DigitalCapacity landlordGoogle CloudHyperscalerBackstop$1.4BGoogle backstops $1.4 billion of Fluidstack's lease obligations at Barber Lake and received warrants for about 5.4% of Cipher.168 MW—Confirmed
sec.govGoogle will backstop $1.4 billion of Fluidstack’s lease obligationschecked 9 Nov 2026
25 Sep 2025FluidstackNeocloudCipher DigitalCapacity landlordColocation lease$3BContracted revenue over the initial 10-year term; in September 2026 the lease was extended to 20 years, taking Barber Lake contracted revenue above $9 billion.168 MW10 yrConfirmed
sec.govThe agreement represents approximately $3 billion in contracted revenue over the initial 10-year termchecked 9 Nov 2026
25 Sep 2025MetaFrontier labCoreWeaveNeocloudCapacity contract$14.2BUp to about $14.2 billion of initial commitments through December 2031, with an option to expand; Meta added a $21 billion commitment in March 2026.—6 yrConfirmed
sec.govMeta has initially committed to pay the Company up to approximately $14.2 billion through December 14, 2031checked 9 Nov 2026
25 Sep 2025OpenAIFrontier labCoreWeaveNeocloudCapacity contract$6.5BUp to $6.5 billion through May 2031, bringing OpenAI's total contract value with CoreWeave to about $22.4 billion.——Confirmed
sec.govOpenAI has committed to pay the Company up to approximately $6.5 billion through May 31, 2031 under the Order Form.checked 9 Nov 2026
22 Sep 2025OpenAIFrontier labNVIDIAChip vendorEquity + computeNVIDIA Vera Rubin$100Bamount reportedLetter of intent for up to $100 billion of Nvidia investment as each gigawatt is deployed; it was not finalised and was replaced in February 2026 by a $30 billion equity investment.10 GW—Reported
nvidianews.nvidia.comNVIDIA intends to invest up to $100 billion in OpenAI as the new NVIDIA systems are deployed.checked 9 Nov 2026
19 Sep 2025MetaFrontier labOracleHyperscalerCapacity contract$20Bamount reportedReported by Bloomberg as talks of about $20 billion; not confirmed as signed.——Reported
deccanchronicle.comOracle is in discussions with Meta for a cloud computing deal worth about $20 billionchecked 9 Nov 2026
16 Sep 2025MicrosoftHyperscalerNscaleNeocloudCapacity contractNVIDIA GB300undisclosed50 MW—Confirmed
nscale.comwill initially house 23,040 NVIDIA GB300 GPUs delivered in Q1 of 2027.checked 10 Nov 2026
16 Sep 2025OpenAIFrontier labNscale (Stargate UK)NeocloudCapacity contractNVIDIAundisclosed8,000 GPUs—Reported
nscale.comOpenAI will explore offtake of up to 8,000 NVIDIA GPUs in Q1 2026checked 9 Nov 2026
9 Sep 2025CoreWeaveNeocloudNVIDIAChip vendorBackstop$6.3BInitial value of the order: Nvidia must buy any capacity CoreWeave leaves unsold through 13 April 2032.—6.6 yrConfirmed
sec.govNVIDIA is obligated to purchase the residual unsold capacity through April 13, 2032.checked 9 Nov 2026
8 Sep 2025MicrosoftHyperscalerNebiusNeocloudCapacity contract$17.4BTotal contract value through 2031; up to about $19.4 billion if Microsoft buys additional services.—5 yrConfirmed
sec.govthe total contract value is about $17.4 billion through 2031.checked 9 Nov 2026
5 Sep 2025NVIDIAChip vendorLambdaNeocloudCapacity contract$1.5Bamount reportedReported by The Information as a four-year leaseback of GPU servers; not confirmed by the companies.18,000 GPUs4 yrReported
tomshardware.comchecked 9 Nov 2026
21 Aug 2025MetaFrontier labGoogle CloudHyperscalerCapacity contract$10Bamount reportedReported by Reuters citing one source as more than $10 billion over six years; not confirmed by the companies.—6 yrReported
ksl.comGoogle has struck a six-year cloud computing deal with Meta Platforms worth more than $10 billionchecked 9 Nov 2026
18 Aug 2025FluidstackNeocloudTeraWulfCapacity landlordColocation lease$6.7BTotal contracted revenue including the CB-5 expansion; lease extensions could raise it to about $16 billion.160 MW10 yrConfirmed
sec.govRepresents $6.7 Billion in Contracted Revenue, with Potential to Reach $16 Billion with Lease Extensionschecked 9 Nov 2026
15 Aug 2025CoreWeaveNeocloudGalaxy DigitalCapacity landlordColocation leaseundisclosed800 MW15 yrConfirmed
galaxy.comCoreWeave has now committed to the full 800 MW of approved power capacitychecked 9 Nov 2026
15 Aug 2025Galaxy Digital (Helios)Capacity landlordUndisclosed lender (reported Deutsche Bank)LenderDebt financing$1.4Bproject financing facility, 80% loan-to-cost, 36-month term; Galaxy funded $350M equity—3 yrConfirmed
galaxy.comtoday announced the closing of a $1.4 billion project financing facilitychecked 9 Nov 2026
14 Aug 2025FluidstackNeocloudTeraWulfCapacity landlordColocation lease$3.7BContracted revenue over the initial 10-year terms; two 5-year options could raise it to about $8.7 billion. Google backstops part of the lease obligations.200 MW10 yrConfirmed
sec.govThe agreements represent approximately $3.7 billion in contracted revenue over the initial 10-year termschecked 9 Nov 2026
14 Aug 2025TeraWulfCapacity landlordGoogle CloudHyperscalerBackstop$1.8BGoogle backstops up to $1.8 billion of Fluidstack's lease obligations and received warrants for about 8% of TeraWulf; on 18 August 2025 both were raised to about $3.2 billion and about 14%.200 MW—Confirmed
sec.govGoogle will backstop $1.8 billion of Fluidstack’s lease obligationschecked 9 Nov 2026
31 Jul 2025CoreWeaveNeocloudMorgan Stanley, MUFG (joint lead arrangers); Goldman Sachs et al.LenderDebt financing$2.6Bdelayed draw term loan (DDTL 3.0), SOFR+4%——Confirmed
sec.govhas closed a $2.6 billion delayed draw term loan facilitychecked 9 Nov 2026
31 Jul 2025OpenAIFrontier labNscale / Aker JV (Stargate Norway)NeocloudCapacity contractNVIDIAundisclosed230 MW—Reported
nscale.comStargate Norway is planned to deliver 230MW of capacity, with ambitions to expand by an additional 290MW.checked 9 Nov 2026
22 Jul 2025OpenAIFrontier labOracleHyperscalerCapacity contract$300Bamount reportedThe 4.5 GW agreement was announced by OpenAI; the $300 billion five-year value was reported by The Wall Street Journal and not confirmed by the companies.4.5 GW5 yrConfirmed
cnbc.comThe Wall Street Journal on Wednesday reported that OpenAI is set to pay Oracle $300 billion over five years.checked 9 Nov 2026
30 Jun 2025SpaceXAIFrontier labBond and loan investors (Morgan Stanley-led per media)LenderDebt financing$5B$3.0B 12.5% senior secured notes due 2030 + $1.0B fixed-rate (12.5%) and $1.0B floating-rate (SOFR+7.25%) term loans due Jun 30 2030—5 yrConfirmed
sec.govissued $3,000 million aggregate principal amount of 12.5% interest Senior Secured Notes due in 2030checked 9 Nov 2026
11 Jun 2025Mistral AINeolabNVIDIAChip vendorGPU purchaseNVIDIA Grace Blackwellundisclosed18,000 GPUs—Confirmed
mistral.aiwith availability of tens of thousands of GPUs, and rapid expansion in the coming years.checked 9 Nov 2026
10 Jun 2025OpenAIFrontier labGoogle CloudHyperscalerCapacity contractundisclosed——Reported
techzine.euchecked 9 Nov 2026
28 May 2025CoreWeaveNeocloudApplied DigitalCapacity landlordColocation lease$7BAbout $7 billion over 15 years for two buildings (250 MW); CoreWeave later took the full 400 MW at Polaris Forge 1, about $11 billion in total.250 MW15 yrConfirmed
sec.govfor the Building 3 Datacenter Lease is expected to be approximately $4 billionchecked 9 Nov 2026
22 May 2025OpenAIFrontier labG42 (Stargate UAE)Sovereign cloudCapacity contractNVIDIA GB300undisclosed1 GW—Confirmed
intelligentcio.comStargate UAE, a 1-gigawatt compute cluster, will be built by G42 and operated by OpenAI and Oracle.checked 9 Nov 2026
21 May 2025CrusoeNeocloudBlue Owl Capital, Primary Digital InfrastructureLenderJoint venture$15B$15 billion is the total size of the joint venture for the Abilene, Texas campus across two phases, not a single loan.1.2 GW—Confirmed
crusoe.aiannounced today the second phase of a $15 billion joint-venture to fund the 1.2 gigawatt AI data center in Abilene, Texas.checked 9 Nov 2026
16 May 2025AnthropicFrontier labMorgan Stanley, Barclays, Citibank, Goldman Sachs, JPMorgan, RBC, MUFGLenderDebt financing$2.5Bfive-year revolving credit line—5 yrConfirmed
nbcsandiego.com$2.5 billion, five-year revolving credit linechecked 9 Nov 2026
15 May 2025OpenAIFrontier labCoreWeaveNeocloudCapacity contract$4BUp to $4 billion, expanding the March 2025 contract.——Confirmed
investors.coreweave.comfollowed by an expanded agreement worth up to $4 billion in May 2025.checked 9 Nov 2026
13 May 2025HUMAINSovereignNVIDIAChip vendorGPU purchaseNVIDIA GB300 Grace Blackwellundisclosed500 MW5 yrConfirmed
nvidianews.nvidia.coma projected capacity of up to 500 megawattschecked 9 Nov 2026
9 Apr 2025Safe SuperintelligenceNeolabGoogle CloudHyperscalerCapacity contractGoogle TPUundisclosed——Confirmed
techcrunch.comchecked 9 Nov 2026
10 Mar 2025OpenAIFrontier labCoreWeaveNeocloudCapacity contract$11.9BUp to $11.9 billion; OpenAI also received $350 million of CoreWeave stock at its IPO.—5 yrConfirmed
wf.coreweave.comThe contract value for this strategic deal is up to $11.9 billion.checked 9 Nov 2026
23 Dec 2024Core42 (G42)SovereignTeraWulfCapacity landlordColocation leaseundisclosed60 MW10 yrConfirmed
investors.terawulf.comCritical IT capacity is as follows: 2 MW for the Wulf Den, 16 MW for CB-1, and 42 MW for CB-2.checked 9 Nov 2026
6 Dec 2024CohereNeolabCoreWeaveNeocloudCapacity contract$512MThe value is Cohere's C$725 million compute project in Canada, converted at about 0.706 USD/CAD; the Government of Canada committed up to C$240 million of it.——Confirmed
betakit.comup to $240 million CAD into Cohere’s $725-million projectchecked 9 Nov 2026
22 Nov 2024AnthropicFrontier labAmazon Web ServicesHyperscalerEquity + computeAWS Trainium (Trainium2)$4BAn additional $4 billion investment in convertible notes paid in tranches, bringing Amazon's total investment in Anthropic to $8 billion.——Confirmed
techcrunch.combrings Amazon’s total investment in Anthropic to $8 billionchecked 9 Nov 2026
3 Oct 2024OpenAIFrontier labJPMorgan Chase, Citi, Goldman Sachs, Morgan Stanley, Santander, Wells Fargo, SMBC, UBS, HSBCLenderDebt financing$4Brevolving credit line; undrawn at closing——Confirmed
engadget.comconfirmed that it has a new $4 billion revolving line of credit.checked 9 Nov 2026
29 Aug 2024MagicNeolabGoogle CloudHyperscalerCapacity contractNVIDIA H100 (Magic-G4, A3 Mega VMs); NVIDIA Grace Blackwell (Magic-G5)undisclosed——Confirmed
cloud.google.comWith Google Cloud, Magic will build its G4 supercomputer utilizing A3 Mega VMs powered by NVIDIA H100 Tensor Core GPUs.checked 9 Nov 2026
3 Jun 2024CoreWeaveNeocloudCore ScientificCapacity landlordColocation leaseundisclosed590 MW12 yrConfirmed
sec.gov~590 MW infrastructure (~800 MW gross)checked 9 Nov 2026
17 May 2024CoreWeaveNeocloudBlackstone (lead); Magnetar, Coatue, Carlyle, CDPQ, DigitalBridge Credit, BlackRock, Eldridge, Great ElmLenderDebt financing$7.5Bdebt financing facility (DDTL 2.0)——Confirmed
investors.coreweave.comsigned a definitive agreement for a $7.5 billion debt financing facility led by funds managed by Blackstonechecked 9 Nov 2026
4 Apr 2024LambdaNeocloudMacquarie (lead); Industrial Development FundingLenderDebt financingNVIDIA H100$500MUp to $500 million through a GPU-backed special purpose vehicle secured by the GPUs and their cash flows.——Confirmed
thestar.com.myLambda has secured a $500 million loan from lenders including Macquarie Groupchecked 9 Nov 2026

How to read deal figures

Value. The number is the contract value as the source states it. Many announcements give a ceiling ("up to $X"), a multi-year total, or a figure that includes optional phases. The note under the value carries that wording.

Capacity. Megawatts are recorded only when the source states them, and as stated: critical IT load and gross site power are different things, and announcements do not always say which.

Financing. Debt and backstop rows show who funds the capacity. They are listed in the table and kept out of the buyer-to-provider diagram, because a loan is not a purchase of compute.

Status. Confirmed means a party to the deal or a filing states it. Reported means an outlet reports it and no party has confirmed. See the status rules.

A deal is missing or a figure is wrong? Send the source.